Eight conditions decide whether a line installs on schedule or sits on the floor waiting for a contractor: compressed air, steam or gas, cooling water, power, floor, clear height, footprint and the site survey. Each one below is given as a working range, so your builder can price it before you place the order.
Each range below is the window our lines are built to work in. Measure your building against all eight: a single missing utility can hold up commissioning even when the machines themselves are ready.
On a complete line the compressed air figure is split across three points: pouring, demolding and conveying. Give your compressor supplier the total, and tell us which of the three sections sit furthest from the compressor.
Utility connections, given as working ranges
| Utility | Connection | Pressure or temperature | Consumption or flow |
|---|---|---|---|
| Compressed air | Shop air line | 0.1–1 MPa | 0.3–10 m³/min |
| Steam | 25–100 mm pipe | 0.3–1 MPa | 100–2,000 kg/h |
| Gas | 75–200 mm pipe | 0.1–0.3 MPa | 10–100 m³/h |
| Cooling water | Inlet and outlet lines | 25–40 °C in, 5–25 °C out | 30–50 t/h |
The voltage and frequency in the table are the ones our lines are built for. Send us your national supply and the capacity you already have installed, and the electrical configuration is matched to it at the quotation stage rather than on site.
Electrical parameters of the line
| Parameter | Requirement |
|---|---|
| Total connected capacity | 10–1,000 kW, depending on the line and its heating method |
| Voltage | 220 V / 380 V / 440 V |
| Frequency | 50 Hz / 60 Hz |
| Phase | 2-phase / 3-phase |
| Dedicated transformer | Selected to match the power supply in your country. Large plants need a dedicated transformer and a voltage stabilizer. |
The footprint above is the space the line occupies once the maintenance aisle and the logistics aisle are counted in. Empty floor area without those aisles is not enough to commission and service a full line.
Building and civil works requirements
| Item | Requirement |
|---|---|
| Minimum clear height | 3,500 mm |
| Floor loading | Standard food factory floor loading |
| Floor flatness | Standard food factory floor flatness |
| Anchor bolts | Not required |
| Ambient temperature | 5–35 °C |
| Minimum footprint including maintenance and logistics aisles | 20,000 mm × 6,000 mm (20 m × 6 m) |
Checking the eight conditions above, and measuring them on site, is the buyer's responsibility before the order is placed. If our engineers are required to travel to the project site to survey it, all costs of that trip are borne by the buyer.
The five questions buyers ask most often about preparing a building for a full line.